Procedures: First
Pass Project Co-Ordination procedures will be prepared and will be
fine-tuned along with commencement of Master Planning phase to suit
Project requirements. The procedures available are - Engineering Deliverables codification - Material codification - Cost codification - Planning & Scheduling
Communication: The various media proposed to be used are - Telecommunication (voice & data transfer) - Electronic (E-Mail) - Courier (hard copies)
A
Local Area Network (LAN) will be available at the project site. A Wide
Area Network with sufficient band with needs to the established. Correspondence within the company & with external agencies will be properly ‘referenced’ with a standard numbering system.
Documentation: A
document centre will be established at the project site. Both hard as
well as soft files will be available. A preliminary document numbering
system will be prepared. This will be fine-tuned along with commencement
of Master Planning phase to suit Project requirements. A state-of-art
reprographics centre needs to be set up to cater to the large volumes.
Material Control: A
preliminary material codification system will be prepared. This will be
fine-tuned along with commencement of Master Planning phase to suit
Project requirements. Stores material software system needs to be
evaluated for material codification. A Procurement System will be
established for evaluation and implementation for requisitioning/PO/Post
Order tracking. If required, this part will be maintained by separate
databases.
Commercial / Cost Control: A
preliminary Cost codification system will be prepared. This will be
fine-tuned along with revisions to the Overall Work Breakdown Structure.
Software interfaces will then need to be identified. Preliminary budget
will be prepared & analysis will be done for approval. This will be
in coordination with the Company's commercial team.
Software Tools: The various software tools proposed to be used are - MS Excel, MS Projects - Other Local Databases - Basic Software Packages (MS-Office etc.) - Any existing systems
Meetings: The meetings proposed to be held are : - Weekly / Fortnightly Review meeting - Monthly Appraisal to Company Management
Reports: The reports that will be generated are : - Weekly / Fortnightly Progress report - Monthly Analytical report - Any Other Special reports from time to time